Unavailable Key Personnel: CoFC Splits from GAO and Finds No Duty for an Offeror to Disclose

Government contractors are often faced with the dilemma of their proposed key personnel becoming unavailable for contract performance, through no fault of their own, at a point after proposal submission but prior to contract award. In such cases, the Government Accountability Office (GAO) has espoused a rule that obligates offerors to advise contracting agencies of material changes in proposed staffing, even after proposal submission. See, e.g., AttainX, Inc., B-419306, B-419306.2, Jan. 12, 2021, 2021 CPD ¶ 21. But a recent decision by the Court of Federal Claims (CoFC) challenges this rule, casting doubt on its basis in law or regulation. 

In Golden IT, LLC v. United States, No. 21-1966C, __ Fed. Cl.__, 2022 WL 334369 (Feb. 4, 2022), the awardee Spatial Front, Inc. (SFI) had proposed an individual (identified in the decision as “Mr. JH”) as a key personnel. At the time of submission, Mr. JH was an SFI employee, but departed the company prior to contract award. Golden IT alleged that SFI’s proposal misrepresented his availability and thus the company’s proposal should have been assigned a weakness. The court, however, concluded otherwise.

In its decision, CoFC Judge Matthew Solomson acknowledged that an offeror is not permitted to knowingly misrepresent a material fact in a proposal for the purpose of winning a government contract. But here, he found that the protestor had not met its burden of proving that SFI had any knowledge prior to proposal submission that Mr. JH intended to leave the company. Thus, there was no evidence that this was a deliberate misrepresentation by SFI.

But what about after proposal submission, prior to award? Addressing the aforementioned GAO rule—requiring offerors to alert agencies of changes in proposed staffing after proposal submission—Judge Solomson declared it to be “without legal basis” and “unfair.” The court emphasized that a proposal is submitted at a certain point in time, and that it is evaluated over what can become a lengthy period. Without question, an offeror should have a reasonable basis for all facts and representations made in its proposal at the time of proposal submission. But circumstances may change after proposal submission, and the government has the discretion to engage in discussions to verify proposal details or extract more information. 

Key to this decision, Judge Solomson asserted that no statute, regulation, or Federal Circuit decision requires offerors to routinely update the government of any changes during the government’s evaluation period. This position stands in stark contrast to GAO’s long-standing rule requiring an offeror to do just that. In reaching his conclusion, Judge Solomson also cited an article authored by a Jenner & Block team in 2018, which argued that “GAO has no jurisdiction to make recommendations to offerors – including a recommendation that an offeror disclose the unavailability of key personnel when the offeror first learns of this after proposal submission.” Instead, the court pointed to the solicitation itself as a guidepost for the extent to which key personnel must commit to an offeror, namely whether the solicitation contained any provisions that required commitment letters from proposed key personnel, constant verification of continued availability, or the requirement to update the Agency regarding departures of any employees proposed as key personnel.

In challenging head-on GAO’s expectation that an offeror notify the agency if a key person becomes unavailable after proposal submission, this decision highlights a conflict between the GAO and CoFC in this area. Could this decision turn the tide in favor of contractors currently stuck between a rock and a hard place when key personnel become unavailable during extended procurements? Until that happens, contractors should be reminded that CoFC decisions are not binding on other CoFC judges or GAO, and GAO has not signaled flexibility in its expectation that an offeror update the government whenever a key person’s status changes. In addition, for disappointed offerors raising key personnel non-availability issues in a protest, GAO may serve as the better forum for these arguments. Jenner & Block will continue to monitor any developments in this area of law.

© 2026 Jenner & Block LLP. Attorney Advertising. Jenner & Block LLP is an Illinois Limited Liability Partnership including professional corporations. This publication, presentation, or event is not intended to provide legal advice but to provide information on legal matters and/or firm news of interest to our clients and colleagues. Readers or attendees should seek specific legal advice before taking any action with respect to matters mentioned in this publication or at this event. The attorney responsible for this communication is Brent E. Kidwell, Jenner & Block LLP, 353 N. Clark Street, Chicago, IL 60654-3456. Prior results do not guarantee a similar outcome. Jenner & Block London LLP, an affiliate of Jenner & Block LLP, is a limited liability partnership established under the laws of the State of Delaware, USA and is authorised and regulated by the Solicitors Regulation Authority with SRA number 615729. Information regarding the data we collect and the rights you have over your data can be found in our Privacy Notice. For further inquiries, please contact dataprotection@jenner.com.

Unavailable Key Personnel: CoFC Splits from GAO and Finds No Duty for an Offeror to Disclose

Government contractors are often faced with the dilemma of their proposed key personnel becoming unavailable for contract performance, through no fault of their own, at a point after proposal submission but prior to contract award. In such cases, the Government Accountability Office (GAO) has espoused a rule that obligates offerors to advise contracting agencies of material changes in proposed staffing, even after proposal submission. See, e.g., AttainX, Inc., B-419306, B-419306.2, Jan. 12, 2021, 2021 CPD ¶ 21. But a recent decision by the Court of Federal Claims (CoFC) challenges this rule, casting doubt on its basis in law or regulation. 

In Golden IT, LLC v. United States, No. 21-1966C, __ Fed. Cl.__, 2022 WL 334369 (Feb. 4, 2022), the awardee Spatial Front, Inc. (SFI) had proposed an individual (identified in the decision as “Mr. JH”) as a key personnel. At the time of submission, Mr. JH was an SFI employee, but departed the company prior to contract award. Golden IT alleged that SFI’s proposal misrepresented his availability and thus the company’s proposal should have been assigned a weakness. The court, however, concluded otherwise.

In its decision, CoFC Judge Matthew Solomson acknowledged that an offeror is not permitted to knowingly misrepresent a material fact in a proposal for the purpose of winning a government contract. But here, he found that the protestor had not met its burden of proving that SFI had any knowledge prior to proposal submission that Mr. JH intended to leave the company. Thus, there was no evidence that this was a deliberate misrepresentation by SFI.

But what about after proposal submission, prior to award? Addressing the aforementioned GAO rule—requiring offerors to alert agencies of changes in proposed staffing after proposal submission—Judge Solomson declared it to be “without legal basis” and “unfair.” The court emphasized that a proposal is submitted at a certain point in time, and that it is evaluated over what can become a lengthy period. Without question, an offeror should have a reasonable basis for all facts and representations made in its proposal at the time of proposal submission. But circumstances may change after proposal submission, and the government has the discretion to engage in discussions to verify proposal details or extract more information. 

Key to this decision, Judge Solomson asserted that no statute, regulation, or Federal Circuit decision requires offerors to routinely update the government of any changes during the government’s evaluation period. This position stands in stark contrast to GAO’s long-standing rule requiring an offeror to do just that. In reaching his conclusion, Judge Solomson also cited an article authored by a Jenner & Block team in 2018, which argued that “GAO has no jurisdiction to make recommendations to offerors – including a recommendation that an offeror disclose the unavailability of key personnel when the offeror first learns of this after proposal submission.” Instead, the court pointed to the solicitation itself as a guidepost for the extent to which key personnel must commit to an offeror, namely whether the solicitation contained any provisions that required commitment letters from proposed key personnel, constant verification of continued availability, or the requirement to update the Agency regarding departures of any employees proposed as key personnel.

In challenging head-on GAO’s expectation that an offeror notify the agency if a key person becomes unavailable after proposal submission, this decision highlights a conflict between the GAO and CoFC in this area. Could this decision turn the tide in favor of contractors currently stuck between a rock and a hard place when key personnel become unavailable during extended procurements? Until that happens, contractors should be reminded that CoFC decisions are not binding on other CoFC judges or GAO, and GAO has not signaled flexibility in its expectation that an offeror update the government whenever a key person’s status changes. In addition, for disappointed offerors raising key personnel non-availability issues in a protest, GAO may serve as the better forum for these arguments. Jenner & Block will continue to monitor any developments in this area of law.

© 2026 Jenner & Block LLP. Attorney Advertising. Jenner & Block LLP is an Illinois Limited Liability Partnership including professional corporations. This publication, presentation, or event is not intended to provide legal advice but to provide information on legal matters and/or firm news of interest to our clients and colleagues. Readers or attendees should seek specific legal advice before taking any action with respect to matters mentioned in this publication or at this event. The attorney responsible for this communication is Brent E. Kidwell, Jenner & Block LLP, 353 N. Clark Street, Chicago, IL 60654-3456. Prior results do not guarantee a similar outcome. Jenner & Block London LLP, an affiliate of Jenner & Block LLP, is a limited liability partnership established under the laws of the State of Delaware, USA and is authorised and regulated by the Solicitors Regulation Authority with SRA number 615729. Information regarding the data we collect and the rights you have over your data can be found in our Privacy Notice. For further inquiries, please contact dataprotection@jenner.com.

News and Insights

Event

Associate Steven Arango to Speak at the Veterans' Legal Career Fair

On September 18, Associate Steven Arango will speak on a panel at the Veterans' Legal Career Fair (VLCF), the only legal career fair in the United States dedicated to veterans, active-duty service members, and military spouses.

September 18, 2026

Publications

In American Banker, Partner Laurel Loomis Rimon Weighs in on OCC's Handling of Fintech Bank Charter Applications

Partner Laurel Loomis Rimon spoke with American Banker about how the Office of the Comptroller of the Currency is approaching bank charter applications from fintechs, amid a growing wave of companies seeking charters from federal regulators.

August 18, 2026

Event

Partner David Greenwald to Speak at PLI Program on Privilege and AI

On August 17, David Greenwald will speak at "Fitting New “Tech” Into the Attorney-Client Privilege and Work Product Protection," a virtual program hosted by the Practising Law Institute (PLI).

August 17, 2026