Client Alert: DoD Issues Final Rule Implementing Enhanced Debriefing Requirement
On March 18, 2022, the Department of Defense (DoD) issued a final rule to amend the Defense Federal Acquisition Regulation Supplement (DFARS) to mandate that DoD provide enhanced postaward debriefings to contractors. As we previously highlighted, these changes to postaward debriefings in DoD procurements originally were partially implemented by a Class Deviation issued by DoD in 2018, and further formalized through a proposed rule issued last May. With this final rule, DoD permanently implements important changes to the postaward debriefing process for defense procurements.
While the final rule tracks the proposed rule in most respects, the final rule contains several notable changes that may impact bid protest timeliness considerations. As highlighted, prior to the final rule, DoD provided enhanced debriefings pursuant to Class Deviation 2018-O0011, which permitted offerors to submit additional questions within 2 business days after receiving their postaward debriefing. Then, the agency would be required to respond in writing within 5 business days after receiving those additional questions. To that end, the proposed rule stated that a debriefing would not be considered closed until “[a]fter the second business day after delivering the debriefing, if no additional questions are received.” Thus, under the proposed rule, each offeror’s “enhanced” timeline automatically would be extended for two days—irrespective of whether that offeror actually submitted additional questions or not.
The final provision at DFARS 215.506-70, however, now dictates that a debriefing is not concluded until the later of: (1) the date the debriefing is delivered; or (2) the date of the agency’s response to the offeror’s additional questions if those questions were timely submitted. Thus, the debriefing is extended only if the offeror submits follow-up questions. And, in turn, DFARS 233.104(c)(1)(D) confirms that the agency is required to implement a stay of performance if a GAO protest is filed within 5 calendar days after a debriefing is “concluded” in accordance with these timeframes.
Beyond the above clarification regarding timeliness, in sum, the final rule sets forth the following requirements DoD agencies must adhere to for any procurement in which an enhanced debriefing is available:
- When timely requested, DoD must provide a debriefing for all contract awards (including task and delivery orders) valued at $10 million or more.
- While these requirements apply to negotiated procurements, including contracts for the acquisition of commercial products and services, they do not apply to contracts valued below the simplified acquisition threshold.
- Although as part of this process DoD agencies shall protect offerors’ confidential information, agencies are required to provide an offeror with a redacted version of the source selection decision document where—
- the offeror is a small business or nontraditional defense contractor, the award is above $10 million, and a copy of the selection decision is requested; or
- for all offerors, where the award is greater than $100 million.
- Within 2 business days after receiving a required debriefing an offeror may submit additional questions.
- Within 5 days after an offeror timely submits additional questions the agency shall respond in writing.
- And, as highlighted, the debriefing will not be considered “closed” until the debriefing is delivered, or if the offeror asks follow-up questions, when the agency answers those questions.
As we have suggested previously, contractors that are able to reap the benefits of DoD’s now-formalized robust debriefing process should do so. Regardless of whether the company is successful in the competition or not, contractors should consider targeted follow-up questions tailored to their unique experiences with that procurement and request a redacted version of the agency’s source selection decision. This information can better equip even a successful contractor to improve its next proposal submission and be a source of useful market intelligence. Conversely, and more immediately, this information can arm an unsuccessful offeror (and its attorneys) with critical insights to better assess the viability of a potential protest.
Jenner & Block’s Government Contracts and Grants lawyers have extensive bid protest experience, including prior service as a supervising bid protest hearing officer at GAO, and stand ready to support any challenges to the award of a government contract. We continue to monitor developments relating to bid protests, and particularly timing considerations for contractors. Please stay tuned for forthcoming additional guidance in this area.
While the final rule tracks the proposed rule in most respects, the final rule contains several notable changes that may impact bid protest timeliness considerations. As highlighted, prior to the final rule, DoD provided enhanced debriefings pursuant to Class Deviation 2018-O0011, which permitted offerors to submit additional questions within 2 business days after receiving their postaward debriefing. Then, the agency would be required to respond in writing within 5 business days after receiving those additional questions. To that end, the proposed rule stated that a debriefing would not be considered closed until “[a]fter the second business day after delivering the debriefing, if no additional questions are received.” Thus, under the proposed rule, each offeror’s “enhanced” timeline automatically would be extended for two days—irrespective of whether that offeror actually submitted additional questions or not.
The final provision at DFARS 215.506-70, however, now dictates that a debriefing is not concluded until the later of: (1) the date the debriefing is delivered; or (2) the date of the agency’s response to the offeror’s additional questions if those questions were timely submitted. Thus, the debriefing is extended only if the offeror submits follow-up questions. And, in turn, DFARS 233.104(c)(1)(D) confirms that the agency is required to implement a stay of performance if a GAO protest is filed within 5 calendar days after a debriefing is “concluded” in accordance with these timeframes.
Beyond the above clarification regarding timeliness, in sum, the final rule sets forth the following requirements DoD agencies must adhere to for any procurement in which an enhanced debriefing is available:
- When timely requested, DoD must provide a debriefing for all contract awards (including task and delivery orders) valued at $10 million or more.
- While these requirements apply to negotiated procurements, including contracts for the acquisition of commercial products and services, they do not apply to contracts valued below the simplified acquisition threshold.
- Although as part of this process DoD agencies shall protect offerors’ confidential information, agencies are required to provide an offeror with a redacted version of the source selection decision document where—
- the offeror is a small business or nontraditional defense contractor, the award is above $10 million, and a copy of the selection decision is requested; or
- for all offerors, where the award is greater than $100 million.
- Within 2 business days after receiving a required debriefing an offeror may submit additional questions.
- Within 5 days after an offeror timely submits additional questions the agency shall respond in writing.
- And, as highlighted, the debriefing will not be considered “closed” until the debriefing is delivered, or if the offeror asks follow-up questions, when the agency answers those questions.
As we have suggested previously, contractors that are able to reap the benefits of DoD’s now-formalized robust debriefing process should do so. Regardless of whether the company is successful in the competition or not, contractors should consider targeted follow-up questions tailored to their unique experiences with that procurement and request a redacted version of the agency’s source selection decision. This information can better equip even a successful contractor to improve its next proposal submission and be a source of useful market intelligence. Conversely, and more immediately, this information can arm an unsuccessful offeror (and its attorneys) with critical insights to better assess the viability of a potential protest.
Jenner & Block’s Government Contracts and Grants lawyers have extensive bid protest experience, including prior service as a supervising bid protest hearing officer at GAO, and stand ready to support any challenges to the award of a government contract. We continue to monitor developments relating to bid protests, and particularly timing considerations for contractors. Please stay tuned for forthcoming additional guidance in this area.
Related Lawyers
Related Capabilities
Related Locations
© 2026 Jenner & Block LLP. Attorney Advertising. Jenner & Block LLP is an Illinois Limited Liability Partnership including professional corporations. This publication, presentation, or event is not intended to provide legal advice but to provide information on legal matters and/or firm news of interest to our clients and colleagues. Readers or attendees should seek specific legal advice before taking any action with respect to matters mentioned in this publication or at this event. The attorney responsible for this communication is Brent E. Kidwell, Jenner & Block LLP, 353 N. Clark Street, Chicago, IL 60654-3456. Prior results do not guarantee a similar outcome. Jenner & Block London LLP, an affiliate of Jenner & Block LLP, is a limited liability partnership established under the laws of the State of Delaware, USA and is authorised and regulated by the Solicitors Regulation Authority with SRA number 615729. Information regarding the data we collect and the rights you have over your data can be found in our Privacy Notice. For further inquiries, please contact dataprotection@jenner.com.
On March 18, 2022, the Department of Defense (DoD) issued a final rule to amend the Defense Federal Acquisition Regulation Supplement (DFARS) to mandate that DoD provide enhanced postaward debriefings to contractors. As we previously highlighted, these changes to postaward debriefings in DoD procurements originally were partially implemented by a Class Deviation issued by DoD in 2018, and further formalized through a proposed rule issued last May. With this final rule, DoD permanently implements important changes to the postaward debriefing process for defense procurements.
While the final rule tracks the proposed rule in most respects, the final rule contains several notable changes that may impact bid protest timeliness considerations. As highlighted, prior to the final rule, DoD provided enhanced debriefings pursuant to Class Deviation 2018-O0011, which permitted offerors to submit additional questions within 2 business days after receiving their postaward debriefing. Then, the agency would be required to respond in writing within 5 business days after receiving those additional questions. To that end, the proposed rule stated that a debriefing would not be considered closed until “[a]fter the second business day after delivering the debriefing, if no additional questions are received.” Thus, under the proposed rule, each offeror’s “enhanced” timeline automatically would be extended for two days—irrespective of whether that offeror actually submitted additional questions or not.
The final provision at DFARS 215.506-70, however, now dictates that a debriefing is not concluded until the later of: (1) the date the debriefing is delivered; or (2) the date of the agency’s response to the offeror’s additional questions if those questions were timely submitted. Thus, the debriefing is extended only if the offeror submits follow-up questions. And, in turn, DFARS 233.104(c)(1)(D) confirms that the agency is required to implement a stay of performance if a GAO protest is filed within 5 calendar days after a debriefing is “concluded” in accordance with these timeframes.
Beyond the above clarification regarding timeliness, in sum, the final rule sets forth the following requirements DoD agencies must adhere to for any procurement in which an enhanced debriefing is available:
- When timely requested, DoD must provide a debriefing for all contract awards (including task and delivery orders) valued at $10 million or more.
- While these requirements apply to negotiated procurements, including contracts for the acquisition of commercial products and services, they do not apply to contracts valued below the simplified acquisition threshold.
- Although as part of this process DoD agencies shall protect offerors’ confidential information, agencies are required to provide an offeror with a redacted version of the source selection decision document where—
- the offeror is a small business or nontraditional defense contractor, the award is above $10 million, and a copy of the selection decision is requested; or
- for all offerors, where the award is greater than $100 million.
- Within 2 business days after receiving a required debriefing an offeror may submit additional questions.
- Within 5 days after an offeror timely submits additional questions the agency shall respond in writing.
- And, as highlighted, the debriefing will not be considered “closed” until the debriefing is delivered, or if the offeror asks follow-up questions, when the agency answers those questions.
As we have suggested previously, contractors that are able to reap the benefits of DoD’s now-formalized robust debriefing process should do so. Regardless of whether the company is successful in the competition or not, contractors should consider targeted follow-up questions tailored to their unique experiences with that procurement and request a redacted version of the agency’s source selection decision. This information can better equip even a successful contractor to improve its next proposal submission and be a source of useful market intelligence. Conversely, and more immediately, this information can arm an unsuccessful offeror (and its attorneys) with critical insights to better assess the viability of a potential protest.
Jenner & Block’s Government Contracts and Grants lawyers have extensive bid protest experience, including prior service as a supervising bid protest hearing officer at GAO, and stand ready to support any challenges to the award of a government contract. We continue to monitor developments relating to bid protests, and particularly timing considerations for contractors. Please stay tuned for forthcoming additional guidance in this area.
While the final rule tracks the proposed rule in most respects, the final rule contains several notable changes that may impact bid protest timeliness considerations. As highlighted, prior to the final rule, DoD provided enhanced debriefings pursuant to Class Deviation 2018-O0011, which permitted offerors to submit additional questions within 2 business days after receiving their postaward debriefing. Then, the agency would be required to respond in writing within 5 business days after receiving those additional questions. To that end, the proposed rule stated that a debriefing would not be considered closed until “[a]fter the second business day after delivering the debriefing, if no additional questions are received.” Thus, under the proposed rule, each offeror’s “enhanced” timeline automatically would be extended for two days—irrespective of whether that offeror actually submitted additional questions or not.
The final provision at DFARS 215.506-70, however, now dictates that a debriefing is not concluded until the later of: (1) the date the debriefing is delivered; or (2) the date of the agency’s response to the offeror’s additional questions if those questions were timely submitted. Thus, the debriefing is extended only if the offeror submits follow-up questions. And, in turn, DFARS 233.104(c)(1)(D) confirms that the agency is required to implement a stay of performance if a GAO protest is filed within 5 calendar days after a debriefing is “concluded” in accordance with these timeframes.
Beyond the above clarification regarding timeliness, in sum, the final rule sets forth the following requirements DoD agencies must adhere to for any procurement in which an enhanced debriefing is available:
- When timely requested, DoD must provide a debriefing for all contract awards (including task and delivery orders) valued at $10 million or more.
- While these requirements apply to negotiated procurements, including contracts for the acquisition of commercial products and services, they do not apply to contracts valued below the simplified acquisition threshold.
- Although as part of this process DoD agencies shall protect offerors’ confidential information, agencies are required to provide an offeror with a redacted version of the source selection decision document where—
- the offeror is a small business or nontraditional defense contractor, the award is above $10 million, and a copy of the selection decision is requested; or
- for all offerors, where the award is greater than $100 million.
- Within 2 business days after receiving a required debriefing an offeror may submit additional questions.
- Within 5 days after an offeror timely submits additional questions the agency shall respond in writing.
- And, as highlighted, the debriefing will not be considered “closed” until the debriefing is delivered, or if the offeror asks follow-up questions, when the agency answers those questions.
As we have suggested previously, contractors that are able to reap the benefits of DoD’s now-formalized robust debriefing process should do so. Regardless of whether the company is successful in the competition or not, contractors should consider targeted follow-up questions tailored to their unique experiences with that procurement and request a redacted version of the agency’s source selection decision. This information can better equip even a successful contractor to improve its next proposal submission and be a source of useful market intelligence. Conversely, and more immediately, this information can arm an unsuccessful offeror (and its attorneys) with critical insights to better assess the viability of a potential protest.
Jenner & Block’s Government Contracts and Grants lawyers have extensive bid protest experience, including prior service as a supervising bid protest hearing officer at GAO, and stand ready to support any challenges to the award of a government contract. We continue to monitor developments relating to bid protests, and particularly timing considerations for contractors. Please stay tuned for forthcoming additional guidance in this area.
Related Lawyers
Related Capabilities
Related Locations
© 2026 Jenner & Block LLP. Attorney Advertising. Jenner & Block LLP is an Illinois Limited Liability Partnership including professional corporations. This publication, presentation, or event is not intended to provide legal advice but to provide information on legal matters and/or firm news of interest to our clients and colleagues. Readers or attendees should seek specific legal advice before taking any action with respect to matters mentioned in this publication or at this event. The attorney responsible for this communication is Brent E. Kidwell, Jenner & Block LLP, 353 N. Clark Street, Chicago, IL 60654-3456. Prior results do not guarantee a similar outcome. Jenner & Block London LLP, an affiliate of Jenner & Block LLP, is a limited liability partnership established under the laws of the State of Delaware, USA and is authorised and regulated by the Solicitors Regulation Authority with SRA number 615729. Information regarding the data we collect and the rights you have over your data can be found in our Privacy Notice. For further inquiries, please contact dataprotection@jenner.com.
News and Insights
Event
Associate Steven Arango to Speak at the Veterans' Legal Career Fair
On September 18, Associate Steven Arango will speak on a panel at the Veterans' Legal Career Fair (VLCF), the only legal career fair in the United States dedicated to veterans, active-duty service members, and military spouses.
September 18, 2026
Publications
In American Banker, Partner Laurel Loomis Rimon Weighs in on OCC's Handling of Fintech Bank Charter Applications
Partner Laurel Loomis Rimon spoke with American Banker about how the Office of the Comptroller of the Currency is approaching bank charter applications from fintechs, amid a growing wave of companies seeking charters from federal regulators.
August 18, 2026
Event
Partner David Greenwald to Speak at PLI Program on Privilege and AI
On August 17, David Greenwald will speak at "Fitting New “Tech” Into the Attorney-Client Privilege and Work Product Protection," a virtual program hosted by the Practising Law Institute (PLI).
August 17, 2026
Publications
Special Counsel Kimberly Cook Featured in FCBA Member Spotlight
The Federal Communications Bar Association (FCBA) featured Kimberly Cook in its Member Spotlight series.
August 13, 2026
Recognition
Three Jenner & Block Partners Named to Crain's New York Business' 2026 Notable Leaders in Accounting, Consulting & Law List
Crain's New York Business recognized Jenner & Block Partners Anthony Barkow, Alison Stein, and Damian Williams among its 2026 Notable Leaders in Accounting, Consulting & Law.
August 10, 2026